NO | PROJECT | LOCATION | ITEM | SCOPE | OWNER | END USER | PROJECT PERIOD |
---|---|---|---|---|---|---|---|
57 | OUMACHE III 1,300 MW CCPP Project | Algeria | AHU: 12sets, ACCU: 12sets, RTU:14sets, ASU:12sets, SAC: 109sets CTHU: 10sets, FAN: 215sets, Control part: 1 Lot, Electric Duct Heater: 10set, Electric Unit Heater: 78sets, Humidifier: 10sets | P | HYENCO | Hyundai E&C | Ongoing (2020.10 ~ 2023.05) |
56 | Algeria Chiller Package Project | Algeria | Air cooled water Chiller: 2sets, Chilled water pump: 4 sets, Heat Exchanger unit: 4 sets, Expansion tank: 2 sets, Control Part, 4sets | P | HYENCO | Hyundai E&C | Ongoing (2021.11 ~ 2022.12) |
55 | Uzbekistan Gas To Liquid Project | Uzbekistan | AHU: 19sets, ACCU: 18sets, PU: 6sets, CFU: 9sets, CCU: 12sets, SAC: 73sets, Fan: 166sets, Steam H/E: 15sets, HWDH: 38sets, Electric Duct Humidifier: 5sets, SUH: 112sets, VAV: 17sets, CAV: 18sets, Blast Protection Damper: 15sets, Expansion Tank: 21sets, St | P | Oltin Yo'l GTL | Hyundai Engineering | Finished (2018.01 ~ 2019.08) |
54 | VinhTan 4 Extension Thermal Power Plant Project (600MW) | VIETNAM | AHU : 4 sets, ACCU : 4 sets, RTU : 4sets, SAC : 16 sets, Fan : 44 sets | P | EVN | Doosan | Finished (May. 2017 ~ Mar. 2018) |
53 | Golon Gas Project | PANAMA | Packaged Air Conditioner : 8 sets, CTHU : 2 sets, FFU : 4 sets Exhaust Fan(Ex-proof) : 2 sets, Duct & Damper, Bulk, Electric : 1 LOT | P | AES | Posco E&C | Finished (Jan. 2017 ~ Aug. 2017) |
52 | VinhTan 4 Thermal Power Plant Project (600MW x 2) | VIETNAM | AHU : 4 sets, ACCU : 4 sets, RTU : 4sets, SAC : 108 sets, Fan : 105 sets | P | EVN | Doosan | Finished (Jun. 2015 ~ Mar. 2017) |
51 | Zubair Project(E-house) | IRAQ | Packaged Air Conditioner(Ex-proof) : 2 sets, Exhaust Fan(Ex-proof) : 4 sets, Exhaust Fan : 1 set | EPC | ENI | Samyang | Finished (2016) |
50 | Satah Al Razboot(SARB) #4 Project(E-HOUSE) | UAE | Roof Top Unit : 27sets, Chemical Filter Unit : 6sets Blast Damper : 27sets, Pressurization Unit : 3sets | EPC | ADMA-OPCO | Hyundai E&C | Finished (2015~2016) |
49 | Zubair Project(LER 3 building) | IRAQ | Packaged Air Conditioner : 6 sets, Sand Trap Box : 3 sets, Panel(Power, Control) : 3 sets | EPC | ENI | Samyang | Finished (2015~2016) |
48 | West Qurna CPPB Project | IRAQ | HVAC SYSTEM (Included Roof top unit : 2sets, PAC : 4sets ) | EPC | LUKOIL | Hyundai | Finished (Sep. 2014 ~ Mar. 2015) |
47 | Clean Fuels Project | KUWAIT | Roof top unit(20RT~30RT) : 6 sets Chemical filter : 3 sets, Inertial filter /w bleed fan : 3 sets Explosion proof fan : 6 sets, Duct & Damper, Bulk, Electric : 1 LOT | EPC | KNPC | KHAN | Finished (Apr. 2014 ~ May. 2015) |
46 | West Qurna Field 2nd Phase Project | IRAQ | Roof top unit(20RT~32RT) : 20 sets PAC(10RT) : 9 sets, Inertial filter /w bleed fan : 10 sets Explosion proof fan : 20 sets, Duct & Damper, Bulk, Electric : 1 LOT | EPC | LUKOIL | Hyundai | Finished (Jan. 2013~Jun. 2013) |
45 | IGD DAS Project | UAE | Damper(Volume Control, Non Return, Pressure Relief, Fire, Gas, Blast, Diffuser, Register, Sound Attenuators, Louver, Sand Trap) : 1 LOT | P | ADGAS | Hyundai | Finished (2011 ~ 2012) |
44 | SHWE field development | MYANMAR | Roof top unit(8RT ~ 61RT) : 13 sets, PAC & Split A/C(1RT ~ 8RT) : 20 sets, Fan(Wall, Duct in line, Roof) : 67 sets | EPC | MOGE | Hyundai | Finished (May. 2010 ~ 2012) |
43 | RAS DJINET CCPP Project (400MW x 3) | ALGERIA | P2 Bulk | P | Sonelgaz SPE | Daewoo E&C | Finished (Jan. 2014 ~ Oct. 2016) |
42 | STX NRC Diesel Power Plant Project (7.5MW x 12) | IRAQ | Air Washer Unit(126,665 CMH, 469kW) : 12 sets | P + Supervisor | NRC | STX | Finished (2012) |
41 | Mong Duong 2_Coal Fired Power Project (560MW x 2) | VIETNAM | Roof top unit(3RT ~ 86RT) : 44 sets AHU(30~40RT ) : 9 sets PAC & Split A/C(1RT ~ 16RT) : 82 sets, Fan(Wall, Roof, Duct in line, Smoke, Explosion proof) : 290 sets Duct & Damper, Bulk, Electric : 1 LOT | EPC | AES-VCM | Doosan | Finished (2012 ~ 2015) |
40 | Raipur TPP Coal Fired Power Plant Project (685MW x 2) | INDIA | Chiller Unit(90RT) : 3 sets, AHU(110RT) : 2 sets Air Washer Unit(300,000 CMH) : 8 sets PAC & Split A/C(1RT ~ 40RT) : 44 sets FAN(Wall, Roof, Duct in line) : 122 sets Duct & Damper, Bulk, Electric : 1 LOT | EPC | GMR | Doosan | Finished (Apr. 2011 ~ 2015) |
39 | Jordan Research & Training Reactor Project | JORDAN | AHU(17RT ~ 69RT) : 6 sets, Chiller Unit(88RT) : 3 sets PAC(5RT ~ 35RT) : 15 sets, Fan : 51 sets Sand Removal Filter : 6 sets, Air Cleaning Unit : 2 sets Filter Train : 28 sets, Hepa Filter Box : 4 sets | P | JAEC | Daewoo E&C | Finished (2013) |
38 | Braka Nuclear Power Plant Units 1&2 | UAE | Air Cleaning Unit : 32 sets, Electric Duct Heater : 32 sets | P | ENEC | KEPCO | Finished (2012 ~ 2021) |